Concrete delivery minimums and short-load fees

How small a ready-mix order can be, when the short-load fee applies, and what it adds to a 1- to 6-yard pour. The figures come from five plants that publish their 2026 schedules and two national cost guides.

Short answer: the plants that publish schedules will deliver as little as 1 to 1.5 cubic yards (one California plant bills a minimum of 1 to 5 yards’ worth by city), but orders below a short-load threshold, usually 3 to 7 yards at the plants below, pay an extra fee. Published plant fees run from $100 to $200 per load. National guides quote it per yard instead: $40–$60/yd (Angi) or +$53/yd under 10 yards (HomeGuide). On a 1-yard order the fees can cost more than the concrete.

Published plant schedules (2026)

Most plants quote by phone. These five publish their minimums and small-load fees, so the numbers can be checked. They are examples from five areas, not a national average.

Minimum order, short-load threshold, and fee as published by each plant
Plant (area), datedSmallest orderShort-load ruleFee
Southern Readymix (8 plants, Georgia)
Viewed Nov 23, 2026
1 yd7 yd or less$150 flat per load; full load 9–10 yd
Quick Mix Concrete (Atlanta area, GA)
Pricing page viewed Nov 23, 2026; examples post Oct 17, 2026
Sold in ½-yd stepsUnder 6 yd$200, plus $95 fuel/environmental per truck
Townsend Concrete (Vacaville, CA)
Viewed Nov 23, 2026
No delivery minimum, but a minimum concrete charge of 1–5 yd ($162–$810) by cityUnder 3–6 yd, by city$100, or the cost of the missing yardage if that is less; delivery $120–$350 per load
L&S Concrete n RediMix (Plummer, Idaho)
Prices as of Jan 1, 2026
Under 1 yd is listedUnder 5 yd (tiers end at 4.75 yd)$200 (<1 yd), $175, $150, $125, down to $100 (4–4.75 yd); delivery $75–$215 per load within 35 miles
HC&D Maui Ready-Mix (Maui, HI)
Effective Feb 1, 2026
1.5 ydUnder 6 ydSliding minimum delivery charge: zone 1 is $121.50 at 1.5 yd, falling to $6.75 at 5.75 yd

What national cost guides say

The two kinds of source don’t match. The guides describe a per-yard surcharge under about 10 yards. The plants that publish a schedule mostly charge a flat fee per load, with lower thresholds. Your plant could use either method, so ask which one it uses.

What a small order adds up to

Totals below are worked only from each plant’s published prices for 3,000 psi concrete, weekday delivery, with no pump, additives, or tax.

Delivered totals from published schedules
OrderQuick Mix, GA (Oct 17, 2026)L&S, ID, within 5 miles (Jan 1, 2026)
1.5 yd$292.50 + $200 + $95 = $587.50 ($392/yd)$281.25 + $175 + $75 = $531.25 ($354/yd)
2 yd$390 + $200 + $95 = $685 ($343/yd)$375 + $150 + $75 = $600 ($300/yd)
3 yd$585 + $200 + $95 = $880 ($293/yd)$562.50 + $125 + $75 = $762.50 ($254/yd)
4.5 yd$877.50 + $200 + $95 = $1,172.50 ($261/yd)$843.75 + $100 + $75 = $1,018.75 ($226/yd)
6 yd$1,170 + $95 = $1,265 ($211/yd)$1,125 + $75 = $1,200 ($200/yd)

Quick Mix’s own post works 1-, 3-, and 4.5-yard examples the same way; its 1-yard total is $490, and the concrete is less than half of it. The point holds at both plants: per-yard cost falls quickly as the order nears the threshold, because the fixed fees are spread over more yards. Compare that with PadCalc’s national planning span of $110–$195 per yard for concrete and typical delivery (cost per yard). That span does not include short-load fees, so small orders often come in above it.

How to keep the fee down

For scale: a 10×10 slab at 4 inches is 1.36 yd³ with 10% extra, and a 10×12 patio is about 1.63 yd³. Both are short loads at every plant above. A 16×40 driveway at 4 inches is 7.90 yd³ before waste, so it may or may not clear the threshold depending on the plant.

Metric and Canadian readers

1 cubic yard = 0.765 m³; 1 m³ = 1.308 yd³. A 6-yard threshold is about 4.6 m³, and a 10-yard truck is about 7.6 m³. Every price on this page is in US dollars from US sources. For Canada, see ready-mix prices per cubic metre in Canada (five posted 2026 plant lists, in CAD) and small-load delivery in Canada, where fees run $50–$400 per truck under about 4 to 7 m³. The concrete calculator also works in metric.

Related

Concrete calculator · Cost per yard · Bags vs. ready-mix · Bags in a yard · Driveway cost · Sources

FAQ

What is the minimum amount of concrete a truck will deliver?

It depends on the plant. Published 2026 schedules we checked start at 1 cubic yard (Southern Readymix, Georgia) or 1.5 yards (HC&D Maui). Townsend Concrete in California sets no delivery minimum but charges a minimum concrete amount of 1 to 5 yards depending on the city. Call the plant before you plan around a number.

What is a short-load fee?

A charge for ordering less than the plant’s short-load threshold, because a truck, driver, and washout cost about the same for 2 yards as for 9. Published thresholds run from 3 to 7 yards at individual plants; national guides describe it as orders under about 10 yards.

How much is a short-load fee for concrete?

Angi (Sep 10, 2026) lists $40–$60 per cubic yard and HomeGuide (Jan 6, 2026) +$53 per cubic yard under 10 yards. Plants that publish their schedules mostly charge a flat fee per load instead: $100 (Townsend, capped), $100–$200 tiered by size (L&S, Idaho), $150 (Southern Readymix, Georgia), and $200 (Quick Mix, Georgia).

Is it cheaper to order a little more concrete to avoid the short-load fee?

Sometimes. If you need 5.5 yards and the threshold is 6, half a yard of extra concrete can cost less than the fee. At Quick Mix’s published prices, half a yard of 3,000 psi is $97.50 against a $200 fee. Townsend caps its fee at the cost of the missing yardage for this reason. Do the subtraction with your plant’s numbers.

How many yards are in a full concrete truck?

About 9 to 10 cubic yards on a standard mixer. Southern Readymix describes a full load as nine to ten yards, Quick Mix counts nine yards as one truck, and Angi describes a truckload as about 10 yards.

How much is a cubic metre in yards?

1 cubic metre is about 1.31 cubic yards, and 1 cubic yard is about 0.76 cubic metres. A 6-yard short-load threshold is about 4.6 m³. Every price on this page is in US dollars from US sources, so it is not a Canadian or metric price.